Project Overview

The project was aimed at providing first-time electricity access to underserved households.   

Scope of Work

  • 62 house connections
  • Pegging out the works
  • Pole planting and hole excavation
  • High Voltage (HV) and Medium Voltage (MV) structures
  • LV structures and stays
  • Transformer installation
  • LV protection and conductor stringing
  • Installation of earthing systems
  • Pole numbering and service boxes
  • Final system commissioning

Project Outcome

The project was successfully completed and commissioned. Despite a 2-5 month delay due to COVID-19 restrictions, all deliverables were achieved within the allocated 4-5 month construction period.

Community Impact

The project provided safe, reliable electrical connections to 62 homes, improving living conditions, enabling modern conveniences, and supporting socio-economic development in Sane Village.